Kenya faces Sh44bn bill to terminate Adani power deal

Kenya faces Sh44bn bill to terminate Adani power deal
In a statement, the 12.6Km line project will evacuate 105MW of geothermal electricity from the Menengai wells and inject it to National Grid at Soilo substation/file

NAIROBI, Kenya, Nov 23 – The government was yet to complete the termination of the controversial Sh95.68 billion electricity transmission deal with India’s Adani Group as of June 2026, nearly two years after President William Ruto announced its cancellation.

The Annual Report on the State of Public-Private Partnerships (PPPs) in Kenya shows that the termination of the contract between the Kenya Electricity Transmission Company (KETRACO) and Adani was still ongoing at the end of the 2025/26 financial year.

The report, published by the PPP Directorate, puts the estimated termination payment for the two transmission-line projects at Sh44 billion as of June 2026.

The projects involved the construction of the 400kV Lessos–Loosuk and 220kV Kisumu (Kibos)–Kakamega–Musaga transmission lines, which had an estimated combined cost of Sh41 billion.

The two projects had already reached commercial close under the proposed 30-year public-private partnership arrangement, which covered their development, financing, construction and operation.

President William Ruto announced on November 21, 2024, that the government had initiated the cancellation of the Adani transmission-line agreement alongside the proposed JKIA expansion deal following public opposition and legal challenges.

However, the latest PPP report indicates that the process had not been completed by June 2026, having started in the 2024/25 financial year.

“During the period under review, there were no project tenders that were cancelled. However, the termination of the contract between KETRACO and Adani for the Transmission Lines project, which commenced in FY 2024/25, was still ongoing as at the end of FY 2025/26,” the report states.

The Sh44 billion estimated termination payment represents a significant cost associated with ending the two agreements, whose combined project value was put at Sh41 billion.